Schedule The state maintains Evans Road, so the Town must submit plans for Department of Transportation review at various stages of the project. The following schedule is tentative. Preliminary plan submittal (25 percent complete) Winter 2001 Right-of-way plan submittal (75 percent complete) Summer 2002 Begin right-of-way and easement negotiations Fall 2003 Final plan submittal (100 percent complete) Winter 2004 Complete right-of-way and easement negotiations; receive Final approval of plans from NCDOT Summer 2005 Begin construction Fall 2005 Complete construction Fall 2006 |