High House Road to James Jackson Avenue

The Town is adding an additional northbound lane on Northwest Maynard Road from just north of High House Road to the creek near James Jackson Avenue. This will complete widening of this segment of Maynard Road to four lanes with a median.

Beginning of construction - Spring 2004
Scheduled completion - Fall 2004
Approximate cost - $800,000